What should a civil construction methodology cover?
How the work will be staged and sequenced, the crews and plant on each activity, how material will be sourced and hauled, how traffic, environment, safety and quality will be managed, how the risks specific to that site will be handled, and how it all fits the program and the price.
What costs a methodology marks?
Text that could apply to any job, a sequence that does not match the drawings or schedule, plant and production rates that do not support the program, and risks listed without a response. Panels notice when a method was not written for their project.
Does the methodology need to match the price?
Yes. Crews, plant, production rates and haul in the method should be the same ones the price is built on. When they disagree, a panel reads it as a contractor who has not thought the job through.